Rolling Turbines and Projects Up into Gigawatts
Wind development happens in megawatts and gets reported in gigawatts. A turbine has an MW nameplate, a project consent is written in MW, an export agreement is in MW — but the board pack, the investor deck and the press release all want the portfolio expressed as a single GW number. Anyone maintaining that spreadsheet does this division several times a week.
What Gets Added Together
Onshore clusters
Offshore arrays
Repowering uplift
Stages of the pipeline
Building a Portfolio Figure from Project Megawatts
The arithmetic is trivial; the discipline is in keeping the stages apart so the gigawatt headline still means something when someone checks it.
Total one stage at a time
Sum the nameplate megawatts of everything in a single stage — operating, say — and type it in the left field. 102, 930, 3500: the gigawatt value appears as you type, and a comma or an extra space in the number is handled without complaint.
Check the count against the turbine rating
Divide the project megawatts by the machine rating to sanity-check the layout: 930 MW at 15 MW a machine is 62 positions, while the same 930 MW built onshore at 3.4 MW would need 274. If the turbine count in the drawing does not match, one of the two numbers is stale.
Reverse to unpack a gigawatt target
Announcements and government targets come in GW. The swap button (↔) runs GW → MW so a 3.5 GW programme becomes 3500 MW, which you can then split across phases the way the construction schedule actually works.
Take the number into the tracker
Copy puts the plain value on the clipboard with no unit attached, ready to drop into a capacity tracker or a slide. Ctrl + C inside either field behaves the same way.
Turbine Ratings and Machines per Gigawatt
Nameplate ratings across four decades of turbine design, with what each one contributes in gigawatts and how many positions a full gigawatt would need.
| Turbine class | Nameplate | Per machine | Machines per 1 GW |
|---|---|---|---|
| Legacy onshore, 1990s–2000s | 1.5 MW | 0.0015 GW | 667 |
| Mid-size onshore | 2.5 MW | 0.0025 GW | 400 |
| Recent onshore average | 3.4 MW | 0.0034 GW | 294 |
| Large onshore / low wind | 6 MW | 0.006 GW | 167 |
| Early offshore fixed-bottom | 8 MW | 0.008 GW | 125 |
| Current offshore workhorse | 15 MW | 0.015 GW | 67 |
| Next-generation offshore | 18 MW | 0.018 GW | 56 |
| Announced offshore prototypes | 22 MW | 0.022 GW | 46 |
The right-hand column is the story of the industry in one line: a gigawatt that once meant 667 machines and 667 foundations now takes 67, or fewer. Fewer positions means fewer sea-bed surveys, fewer cable runs and fewer installation days — which is why nameplate ratings kept climbing even after the rotors became awkward to transport.
Handy When the Capacity Sheet Is Open
Project megawatts to portfolio gigawatts as you type
Paste each stage total in turn and read the GW figure straight off, without clearing the field between projects.
Unpack a gigawatt target back into phases
Swapping direction gives GW → MW, the way round you need when a published target has to be reconciled with a build programme.
Kilowatts too, for the small legacy sites
The searchable dropdowns carry every power unit, so a 600 kW machine from an old wind cluster drops into the same calculation as a 22 MW prototype.
Values that paste into the pipeline sheet
Up to eight decimals are kept, so 3.4 MW does not collapse to 0.00 GW, and copy hands over the number alone.
Wind Portfolio Questions
Does a 1 GW wind farm actually deliver 1 GW?
Only in the wind band where every machine is at rated output, which is a minority of the year. The gigawatt is the sum of the nameplates. Averaged over a year an onshore fleet typically settles around a third of that and a modern offshore one around half, so 1 GW installed is closer to 350 MW or 500 MW of average delivery.
What capacity factor should I assume for onshore versus offshore?
As a planning rule of thumb, 30–40 % onshore depending on the site and the rotor-to-generator ratio, and 45–55 % for recent fixed-bottom offshore, with the best sites and largest machines quoted higher still. Modern low-wind onshore turbines lift the factor by fitting a big rotor to a modest generator, so a lower nameplate can post a better percentage.
Why did offshore turbines grow from 8 MW to over 20 MW?
Because the expensive parts offshore are per position, not per megawatt. Foundation, cable, vessel time and consenting cost roughly the same whether the machine on top is 8 or 18 MW, so halving the number of positions in a gigawatt halves a large slice of the capital cost. Swept area rises with the square of the rotor radius, which is where the extra megawatts come from.
What does a developer mean by a 5 GW pipeline?
Everything the company is working on, from sites with turbines already turning to leases with nothing but a boundary on a map. Read the split before the headline: operating capacity earns revenue now, consented capacity has planning permission, and early-stage capacity is an option that may never be built. Two developers claiming the same gigawatts can be in very different businesses.
How many machines sit behind a gigawatt of capacity today?
Offshore, about 67 at the 15 MW rating now going into the water, dropping toward 46 as 22 MW machines arrive. Onshore it is several hundred: at the 3.4 MW class that is 294 positions, which is why land-based gigawatts are assembled from many separate projects rather than one array.
No comments yet. Be the first to comment!