Adding Charger Kilowatts Up into a Site Connection
Every charge point on a depot or hub is specified in kilowatts — 7.4, 11, 22, 50, 150, 350. The distribution network operator, on the other hand, wants one number in megawatts on the connection application. Somewhere between the stall schedule and that form the arithmetic has to happen, and it is the same sum whether you are electrifying six vans behind a builder's merchant or forty tractor units at a logistics park.
Where the Kilowatts Accumulate
Slow AC posts on long dwell
DC bays on short dwell
Depot yards that plug in together
Heavy-vehicle dispensers
Turning a Stall Schedule into a Connection Figure
Work from the stall list you already have rather than a guess about the future, and keep each allowance as its own number so the assumptions stay visible when the design is questioned.
Enter the connected total in kilowatts
Multiply each charger class by its point count, add them up and type the sum in the left field. A mixed site of 20 × 22 kW plus 6 × 150 kW is 440 + 900 = 1340 kW, and the megawatt value appears as you type. A comma works as a decimal separator and spaces are ignored, so pasting 1 340 is fine.
Run the diversified figure as a second number
Convert the raw connected load first, then convert the diversified one. At a 0.6 factor that same 1340 kW becomes 804 kW, or 0.804 MW — quoting both tells the network operator what you installed and what you expect to import.
Reverse when the offer comes back in megawatts
Connection offers and transformer ratings arrive in MW or MVA. Press the swap button (↔) to run MW → kW and see how many charge points a 2 MW offer really supports — 2000 kW is thirteen 150 kW bays with a little left over for lighting and the shop.
Copy the plain number onto the form
The copy button hands over the bare figure with no unit and no spaces, which is what an application field or a load spreadsheet expects. Ctrl + C inside a field does the same thing.
Charger Classes and What a Full Bank Draws
Per-point ratings you will meet in catalogues, each with a realistic stall count and the resulting site total in both units.
| Charge point class | Per point | Points | Site total |
|---|---|---|---|
| AC single-phase, 32 A | 7.4 kW | 40 | 296 kW = 0.296 MW |
| AC three-phase, 16 A | 11 kW | 40 | 440 kW = 0.44 MW |
| AC three-phase, 32 A | 22 kW | 24 | 528 kW = 0.528 MW |
| DC rapid | 50 kW | 8 | 400 kW = 0.4 MW |
| DC high-power | 150 kW | 6 | 900 kW = 0.9 MW |
| DC ultra-rapid bank | 350 kW | 4 | 1400 kW = 1.4 MW |
| DC ultra-rapid hub | 350 kW | 10 | 3500 kW = 3.5 MW |
| Heavy-vehicle dispenser | 1000 kW | 4 | 4000 kW = 4 MW |
Read down the last column and the pattern is plain: forty AC posts and one bank of four ultra-rapids differ by nearly five times in installed capacity while taking up similar amounts of tarmac. The charger mix, not the stall count, is what decides whether a site stays a low-voltage job or needs its own transformer on a medium-voltage feed.
What Helps While Sizing the Supply
Running totals as the stall list grows
Type each revised kilowatt subtotal straight over the last one and the megawatt figure follows immediately, so a phase-one and a phase-two layout can be compared in seconds.
Back to kilowatts when the offer is in MW
Swapping direction turns a quoted 1.5 or 3 MW capacity into kilowatts you can divide by charger rating to see how many bays it really carries.
Any power unit for the ancillary loads
The searchable dropdowns also hold watts, gigawatts, horsepower and BTU/h, so canopy lighting or a compressor rating can go through the same two fields.
Figures clean enough for the application form
Results carry up to eight decimals with spaced thousands, and the copy button strips everything except the digits.
Depot Electrification Questions
Does a 30-point depot really need a 0.33 MW connection?
Only if every post can run flat out at once. 30 × 11 kW is 330 kW of connected load, but a fleet that plugs in overnight has hours in which to share the energy, so such a yard is normally built with active load management and an import limit nearer 0.2 MW. The connected figure still matters for cable sizing, protection and the fault study — it is the import limit that gets negotiated down.
What diversity factor is realistic for overnight fleet charging?
Roughly 0.5 to 0.7 for a managed depot with twenty or more points, and 0.7 to 0.8 for a smaller site of four to ten. Uncontrolled charging is the awkward case: if every vehicle returns at 18:00 and plugs in, the factor approaches 1.0 for that half hour and the transformer ends up 30–40 % larger for a peak nobody benefits from.
At what site total does a charging hub need its own transformer?
Low-voltage connections thin out somewhere in the high hundreds of kilowatts, so once a site passes roughly 0.5 MW it is generally a dedicated substation on a medium-voltage feed. Remember that a transformer is rated in kVA or MVA rather than MW: at 0.95 power factor a 1 MW charging load asks for about 1.05 MVA before any headroom, and most designers then round up to the next standard frame size.
How much capacity does megawatt charging for trucks add to a site?
A great deal. MCS dispensers are specified from about 1000 kW upward, and a truck stop with a handful of them is planned around an aggregate installed capacity somewhere in the 5–20 MW band. In kilowatt terms one dispenser equals roughly 91 of the 11 kW posts you would fit in a car park, which is why these sites are treated as industrial connections rather than retail ones.
Can load management keep a growing depot inside its existing supply?
Frequently, and it is the cheapest capacity available. A dynamic controller measures the whole site's import and shares whatever headroom is left between the charge points, throttling them instead of tripping the main breaker. It buys stalls and time, not energy: if a fleet needs 4000 kWh before dawn and the connection allows 0.2 MW, a twenty-hour charging window is a hard limit no controller can move.
No comments yet. Be the first to comment!